- Construction of a new pipe pile supported fishing pier:
• Use of a barge and crane with a full template system.
• Furnish and install 31 each concrete filled 12″ pipe x .312 wall x 45′ long
• Steel supports and top plates installed to attach treated timber headers for the deck.
• Furnish and install treated timber substructure and decking complete with bench structures.
• Furnish and install underground power and service leading to dock lighting. - 279 LFT of shoreline remediation including the placement of 1300 tons of 4×8 stone and MDOT plain rip rap.
- Installation of concrete plank kayak launch ramp.
- Temporary sheeting piling utilized to install a new 36″ dia. outfall with fabric and stone base.
- Temporary road, site work, bioswales, concrete sidewalks, restoration.