MARINE

DTE River Rouge Power Plant - Decontamination & Demolition
River Rouge, MI

2024
  • Revisions to the Intake Structure:
    • Installation and removal of skimmer structure w/appurtenances.
    • Removal of trash racks.
    • Furnish/install approx. 146 LFT of PCZ18 x 55′ long with waler and connecting to existing pipe struts.
    • Furnish/Install approximately 5,300 tons of 1x3stone/ riprap.
    • Restoration of bank.
  • Revisions to the Outlet Canal Structure:
    • Installation of SSP Outlet Control Structure with steel framing and valves.
    • Removal of steel sheet pile structure and appurtenances.
    • Installation of 16″ pipe.
    • Installation of approximately 5,500 tons of 1x3stone/riprap.
    • Restoration of bank.
  • Removal of Dock Structure:
    • Includes the removal and disposal of seventeen (17) pile clusters.
    • Removal and disposal of approx. 700 LFT of dock structure including decking, railing, bracing, support structure and steel cable.
    • Removal and disposal of Oil Onloading Building Foundation.
  • Shoreline restoration at Outfall 005 includes clearing of all vegetation and installation of 1,025 tons of 1×3 stone/heavy riprap