ECKorneffelLogo
Previous
Next

EARTH RETENTION

Easterly Water Treatment Plant
Cleveland, OH

2014
  • Furnishing and installation of 3,000 LFT of temporary and permanent steel sheet piling
  • Supporting excavation depth varying from 14’ to 17’
  • Wall is supported by a combination of internal bracing (wale and pipe struts) and cantilevered sheet piling
Previous
Next

EARTH RETENTION

Easterly Water Treatment Plant
Cleveland, OH

2014
  • Furnishing and installation of 3,000 LFT of temporary and permanent steel sheet piling
  • Supporting excavation depth varying from 14’ to 17’
  • Wall is supported by a combination of internal bracing (wale and pipe struts) and cantilevered sheet piling