MARINE
Erma Henderson Park
City of Detroit
Detroit, MI
2021
- Removed and disposed of 540 lft
of existing concrete seawall and 760 cy of material behind seawall
- Install 50 lft of sheeting
seawall at east end of Park. Place fence on top of new seawall
- Furnish and place 3400 tons of
1×3 stone and 2100 tons of MDOT plain riprap as shoreline protection
- Raised grade and restored park
area with 11,500 Syd. of 6″ topsoil, seed and mulch
Previous slide
Next slide
MARINE
Erma Henderson Park
City of Detroit
Detroit, MI
2021
- Removed and disposed of 540 lft
of existing concrete seawall and 760 cy of material behind seawall
- Install 50 lft of sheeting
seawall at east end of Park. Place fence on top of new seawall
- Furnish and place 3400 tons of
1×3 stone and 2100 tons of MDOT plain riprap as shoreline protection
- Raised grade and restored park
area with 11,500 Syd. of 6″ topsoil, seed and mulch
PROJECTS
Grosse Pointe Yacht Club (GPYC) Phase 3A/3C : 2021/2022
Blossom Heath Park Pier: 2021/2022
Sugar Island Restoration: 2021-2023
DTE EES Coke – Emergency Shore Line Repair: 2021
Erma Henderson Park City of Detroit: 2021
Celeron Island Restoration: 2018-2019
Detroit Riverfront Conservancy: 2019
DTE Station A Remediation: 2018
PAST PROJECTS
Grosse Pointe Yacht Club: 2016-2017
Riverfront Dock & Fishing Pier: 2015-2016
Fort Street Over the River Bascule Bridge Replacement: 2013-2014