MARINE

Blossom Heath Park Pier
St. Clair Shores, MI

2021/2022
  • New offshore pier construction
      • Three (3) cofferdams – 7,000 SFT of PZC13
      • 26 each 20” pipe piles x 50’ long with W14 supporting headers
      • Structural steel complete with full composite decking
      • 2,000 tons of rip rap
      • Shade structures
      • Landscape feature 
  • 600 LFT of new PZ 27 sheet piling
  • New 375’ long boardwalk supported on 60 each pipe piles
  • New custom railing provided manufactured and installed by Future Fence
  • 2,000 tons of additional rip rap for tie protection
  • Site work, landscaping, pavers, railings, electrical complete
  • New concrete and HMA parking lot

Previous slide
Next slide

MARINE

Blossom Heath Park Pier
St. Clair Shores, MI

2021/2022
  • New offshore pier construction
      • Three (3) cofferdams – 7,000 SFT of PZC13
      • 26 each 20” pipe piles x 50’ long with W14 supporting headers
      • Structural steel complete with full composite decking
      • 2,000 tons of rip rap
      • Shade structures
      • Landscape feature 
  • 600 LFT of new PZ 27 sheet piling
  • New 375’ long boardwalk supported on 60 each pipe piles
  • New custom railing provided manufactured and installed by Future Fence
  • 2,000 tons of additional rip rap for tie protection
  • Site work, landscaping, pavers, railings, electrical complete
  • New concrete and HMA parking lot