DTE Station A Remediation
Detroit, MI
2018
- 500′ of NZ26 x 50′ steel sheet piling for deadman wall with W21 x 101 waler installed on existing PZ 35 sheet piling supporting 30′ excavation against Detroit River
- W24 x 76 King Piles @ 24′ O.C. interlocking with NZ26 and intermediate internal NZ19 sheet piling walls • Interlock sealant applied to sheet piling locks
- 8″ HSS diagonal tube bracing at 24′ O.C. cast in Tremie concrete
- 5,400 yards of Tremie poured in six (6) pours to encase the diagonal brace 30′ below existing grade
PROJECTS
Grosse Pointe Yacht Club (GPYC) Phase 3A/3C : 2021/2022
Blossom Heath Park Pier: 2021/2022
Sugar Island Restoration: 2021-2023
DTE EES Coke – Emergency Shore Line Repair: 2021
Erma Henderson Park City of Detroit: 2021
Celeron Island Restoration: 2018-2019
Detroit Riverfront Conservancy: 2019
DTE Station A Remediation: 2018
PAST PROJECTS
Grosse Pointe Yacht Club: 2016-2017
Riverfront Dock & Fishing Pier: 2015-2016
Fort Street Over the River Bascule Bridge Replacement: 2013-2014