EARTH RETENTION

Ferndale Development of Troy
Ferndale, MI

2019
  • 932 LFT of driven/drilled solider pile & lagging to support an excavation up to 21′
  • Installation of 122 each 14hp73/14hp89/14hp102 piles up to 35′ long
  • 14hp102 double waler and 24″ steel pipe pile struts up to 84′ long each installed
  • Furn/install 17,000 sft of lagging boards