BRIDGE/SOUND WALL

MDOT Bluebill Street Bridge
St. Clair, MI

2024
  • Design and Installation of temporary bridge prior to demolition of old structure.
  • Removal of old bridge once new temporary 1-way structure was complete.
  • Four “L” shaped (4) quadrants and one (1) wall of new galvanized sheeting piling .
  • Backwalls, 6 Tub girders, deck, railings, approach slabs.
  • Excavation, backfill, channel excavation, rip rap, and HMA.