BRIDGE/SOUND WALL
MDOT - Merriman Rd. Over Tarabusi Creek
Livonia, MI
2022
- Reconstruction of bridge under full closure
- Demolition of cast in place 3-span structure
- 12,500 SFT of steel sheet piling and 6,000 LF of 12hp53 h-piles
- New abutments (500 CYD), 27” box beams, wingwalls, deck (205 CYD), railing, approach slabs
- Excavation, backfill, utility location, and sewer work
- 800 tons of rip rap
Previous slide
Next slide
BRIDGE/SOUND WALL
MDOT - Merriman Rd. Over Tarabusi Creek
Livonia, MI
2022
- Reconstruction of bridge under full closure
- Demolition of cast in place 3-span structure
- 12,500 SFT of steel sheet piling and 6,000 LF of 12hp53 h-piles
- New abutments (500 CYD), 27” box beams, wingwalls, deck (205 CYD), railing, approach slabs
- Excavation, backfill, utility location, and sewer work
- 800 tons of rip rap
PROJECTS
Goddard Rd. Over Sexton Kilfoil Drain: 2021
MDOT – Middlebelt Rd. Over Bell Creek: 2022
MDOT – Merriman Rd. Over Tarabusl Creek: 2022
East River Rd. Over North Hickory Canal: 2020
FCA Jeep Plant Sound Wall: 2019
River Rouge Oxbow Restoration Project – Phase III: 2018-2019
PROJECTS
Goddard Rd. Over Sexton Kilfoil Drain: 2021
MDOT – Middlebelt Rd. Over Bell Creek: 2022
MDOT – Merriman Rd. Over Tarabusl Creek: 2022
East River Rd. Over North Hickory Canal: 2020
FCA Jeep Plant Sound Wall: 2019
River Rouge Oxbow Restoration Project – Phase III: 2018-2019
Cherry Lawn Over I-96 Pedestrian Bridge: 2016
Oakland Avenue Over M-8 (3 bridge package): 2015
PAST PROJECTS