BRIDGE/SOUND WALL
FCA Jeep Plant Sound Wall
Detroit, MI
2019
- Design/Build project for 7,500 LFT of sound wall for new FCA Jeep Plant
- Drill 326 each 3′ dia. caissons
- Set four (4) anchor bolts up to 54,” re-steel cages, and concrete fill in each caisson
- Procure, handle, and set 102,667 SFT of sound wall panel within eighty (80) days.
- 30,850 SFT of 10’ tall wall – 260 panels
- 51,405 SFT of 15’ tall wall – 286 panels
- 20,412 SFT of 18’ tall wall – 150 panels
Previous slide
Next slide
BRIDGE/SOUND WALL
FCA Jeep Plant Sound Wall
Detroit, MI
2019
- Design/Build project for 7,500 LFT of sound wall for new FCA Jeep Plant
- Drill 326 each 3′ dia. caissons
- Set four (4) anchor bolts up to 54,” re-steel cages, and concrete fill in each caisson
- Procure, handle, and set 102,667 SFT of sound wall panel within eighty (80) days.
- 30,850 SFT of 10’ tall wall – 260 panels
- 51,405 SFT of 15’ tall wall – 286 panels
- 20,412 SFT of 18’ tall wall – 150 panels
PROJECTS
Goddard Rd. Over Sexton Kilfoil Drain: 2021
MDOT – Middlebelt Rd. Over Bell Creek: 2022
MDOT – Merriman Rd. Over Tarabusl Creek: 2022
East River Rd. Over North Hickory Canal: 2020
FCA Jeep Plant Sound Wall: 2019
River Rouge Oxbow Restoration Project – Phase III: 2018-2019
PROJECTS
Goddard Rd. Over Sexton Kilfoil Drain: 2021
MDOT – Middlebelt Rd. Over Bell Creek: 2022
MDOT – Merriman Rd. Over Tarabusl Creek: 2022
East River Rd. Over North Hickory Canal: 2020
FCA Jeep Plant Sound Wall: 2019
River Rouge Oxbow Restoration Project – Phase III: 2018-2019
Cherry Lawn Over I-96 Pedestrian Bridge: 2016
Oakland Avenue Over M-8 (3 bridge package): 2015
PAST PROJECTS