Marathon Detroit Heavy Oil Upgrade Program 
Detroit, MI
2008 - 2010

  • Furnishing and installation of 7,700 full length 95' h-piles 
  • Furnishing and installation of multipe steel sheet piling pits with interior sheeting walls and two (2) levels of bracing.
  • System is designed to support an excavation depth in excess of 20' in soil conditions with unconfined compressive strengths of less than 500 psf. 
  • Furnishing and installation of in excess of 500 piles in low headroom and restricted access areas.