PILING/DRILLING

Central Energy Plant
Dearborn, MI

2018
  • 305 each 24″ ACIP x 90′ long for the CEP Building (175 tons static/10 ton lateral)
  • 197 each 24″ ACIP x 90′ long for the TES Tank (175 tons static/10 ton lateral)
  • Two (2) Static Load & Two (2) lateral load test
  • 98 each 14hp73 x 115′ long H-piles
  • 45 each 12hp53 x 115′ long H-piles